Figure 1 - Resources module without planning on the weekends
Figure 2 - "Planning on Weekend" setting
Cause
Companies do not use the resources module on the weekend's and when doing their planning regarding the team the documents duration and workload is taking into account the weekends. For this purpose, the setting planning on weekends will enable or disable this functionality.
Prevent Future Issues
Non-applicable
Configurations
On the system configuration:
- Disable the setting the role "Planning on Weekend";
Proposed Tests
- Go to the resources module
- Verify that on the available jobs the workload and the duration is not taking into account the weekends.
Historical Data
Non-applicable
Comments
0 comments
Please sign in to leave a comment.