Figure 1 - Gant view of Jobs
Cause
Users are creating jobs in the Gantt view and when create the job always stays has a son of the selected.
Prevent Future Issues
Non-applicable
Configurations
Go to the user form and:
- Add the role "ProjectSave" and "DeliverableSave"
Proposed Tests
- Go to Gantt and select a task.
- Add new task and check that the new task is created as a sibling of the document that it's currently selected.
- Save
- Leave and reenter view - changes must be persisted.
Historical Data
Non-applicable
Comments
0 comments